Electricity production figures announced for Soyugbulag small HPP in Kalbajar
Energy
- 25 August, 2025
- 12:50
Add Report.az to preferred Google sources
Stay up to date with the top news!
Since its commissioning, the Soyugbulag Small Hydropower Plant (HPP) on the Tartar River in Kalbajar district has generated 42 million kWh of electricity as of July 1.
Report informs, citing the Ministry of Energy, that the Soyugbulag HPP was commissioned on August 25, 2023.
The plant is a derivation-type high-pressure facility with a total capacity of 5.3 MW, comprising two hydro units, each with a capacity of 2.65 MW.
Kəlbəcərdəki “Soyuqbulaq” KSES-də istehsal olunan enerjinin həcmi açıqlanıb
Назван объем производства электроэнергии на МГЭС "Союгбулаг" в Кяльбаджаре
Latest News
16:44
Norway contributes €46.3 million to Ukraine Energy Support Fund
Other countries
16:41
Merz urges EU to focus its budget on security, competitiveness
Other countries
16:22
Azerbaijan weather forecast for November 26
Ecology
16:05
Two men charged over suspected burglary at William and Kate's Norfolk home
Other countries
15:50
International Training Center for Forestry and Nursery Management to be established in Azerbaijan
Domestic policy
15:40
Ilham Aliyev extends condolences to family of Hikmet Cetin
Domestic policy
15:34
Lukashenko describes Europe's participation in negotiations between Russia and Ukraine as progress
Other countries
15:12
Video
Documentary film 'Vətən daşı' available on YouTube
Karabakh
15:07
Ilham Aliyev's social media accounts share video of his meeting with Lithuanian FM
Foreign policy